Project overview
Following a reported loss of heating in the communal areas of a sheltered accommodation block, an investigation identified the root cause as a failure in the distribution equipment.
The existing switchgear had exceeded its operational lifespan, approaching 30 years old, and was long discontinued. Given the critical nature of the supply, a full replacement was deemed the most effective solution.
Scope of work
The project involved replacing two mains distribution rooms to ensure reliable power delivery and mitigate future failures. Given the extensive nature of the replacement, a scheduled shutdown of all communal areas was required.
Key considerations included minimizing disruption to residents while ensuring essential services remained operational throughout the works.
Implementation strategy
-
Temporary supply installation: Site temporary supplies were installed to maintain critical services such as emergency lighting, alarms, and heating in occupied areas.
-
Shutdown & removal: A structured shutdown plan was executed, allowing the removal of the outdated switchgear while maintaining safety for residents and staff.
-
Equipment replacement & installation: New distribution switchgear was installed, tested, and commissioned to restore full functionality.
-
Extended work hours: Given the complexity and urgency of the project, extended working hours were required to meet deadlines and ensure timely completion.


Challenges & solutions
-
Resident welfare & disruption management
• Communication strategies, including early notifications and resident briefings, were employed to ensure understanding and cooperation.
• Essential services remained operational via temporary supplies, reducing discomfort. -
Logistics & coordination
• Careful scheduling ensured equipment delivery and installation proceeded without delay.
• Close collaboration with suppliers and contractors minimized downtime. -
Time constraints
• Work was carried out continuously to meet the ambitious one-week completion timeframe.
• Additional skilled personnel were deployed to accelerate progress.

Outcome
The replacement was successfully completed and commissioned within the planned week. As a result, the communal areas regained reliable heating and power distribution, improving the overall safety and comfort of residents. The new switchgear provides long-term operational security, reducing the risk of similar failures in the future.
For more information or to discuss your project requirements, please contact us today.